Harris County officials on Thursday disputed an estimate released this week showing it would cost $29 million to implode the vacant Reliant Astrodome and build a 1,600-space parking lot in two and a half years.
The figure, calculated by local firms Linbeck Construction and Walter P. Moore and Associates after a three-month study commissioned by the Houston Texans and the Houston Livestock Show and Rodeo, is less than half the estimated price tag released last year by consultants hired by the Harris County Sports and Convention Corp., the county agency that runs Reliant Park.
During a media tour of the 48-year-old condemned facility on Thursday, Sports Corp. Chairman Edgar Colon suggested that the latest estimate did not take into account all the costs that would be incurred in blowing up the behemoth structure, on which the county still owes some $30 million in construction debt but has sat vacant since 2000 when the Houston Astros moved to Minute Maid Park downtown.
“There’s more to it than just $29 million,” Colon said. “You have to look through it, the things that they exclude explicitly. I’m not challenging the credibility of their experts, I’m just saying that we have to have our own experts look at those numbers.”
Linbeck Vice President John Go said the firms stand by the findings of the study and the price tag.
“The Houston Texans and the Rodeo asked us to develop a methodology and a report that will stand up against questions because they knew that someone might question it,” Go said, noting that Walter P. Moore was the structural engineer when the stadium was built in the mid-1960s and again when it was expanded in 1989.
I rather doubt there’s anything seriously wrong with the methodology used in this estimate. Even County Judge Ed Emmett admitted after the Rodeo/Texans report came out that the previous estimate of demolition costs by the county had been too high. His complaint was that the report didn’t present any other options for what to do with the Dome, and that until the question of what to do with it is settled it’s premature to talk about demolition. When might we get a decision from Comissioner’s Court about what to do?
Pressed by reporters, Colon declined to give a firm time line for when the agency may bring a proposal to commissioners but said he hopes it does not take more than five years.
Colon said part of the reason the decision has been delayed is that interest from developers in rehabilitating the site dropped off during the recession, but he said it is increasing again with the improving economy, and the Sports Corp. is receiving and evaluating new ideas.
“What I think is that it’s in the best interest of the taxpayer to continue to explore all the options in order to make a decision,” said Colon, who brushed off concerns raised by the Texans and Rodeo that the aging, vacant Astrodome would hurt Houston’s chances of getting to host the Super Bowl in 2017.
NFL Commissioner Roger Goodell dropped that hint about converting the Dome into parking at the NFL owners’ meeting. Commissioners Court hasn’t indicated they’re in any rush to make a decision, so I guess they’re not too concerned about that, either. All I know is that at this point we’re in agreement that demolishing the Dome won’t be that expensive. The question is what if anything are the viable alternatives to demolition. It would be nice to get some answers to that sooner rather than later. Hair Balls and Campos have more.