Metro still fixing rail car issues

Someday this will all be over.

Houston’s light rail system is fully open, but closing out a complicated rail car purchase that nearly derailed the new lines remains a challenge for transit officials.

Metropolitan Transit Authority officials continue withholding $12.9 million from CAF U.S.A. – the builder of the vehicles – as they debate the amount of liquidated damages owed because of delays and delivery of railcars that were overweight, leaky and halted by faulty axles, among other problems.

When those discussions could conclude and what sort of damages Metro could receive is uncertain, transit agency CEO Tom Lambert said.

“We are not there yet,” he said. “We are going to continue to work with CAF, address the issues and go from there.”

In the meantime, the Metro board on Thursday extended a contract with Parsons Transportation Group, an engineering and design firm, for oversight of the CAF purchase. The extension carries the contract beyond its previous expiration in May to April 2018 and adds nearly $700,000 to the contract, which has already paid Parsons $29.6 million.

All 39 of the new light rail cars purchased are available for service, and carried a higher-than-normal number of passengers because of the Houston Livestock Show and Rodeo.

All of the cars, however, also have a handful of fleet defects that CAF will have to correct, said Scott Grogan, Metro’s senior director of rail operations.

[…]

The cars are only part of the stumbles related to the rail lines that Metro has raced to correct. Axle counters along the line led to delays in service for months, dropping on-time performance, especially on the Red Line, which represents most rail trips.

Timing has improved significantly since a blitz of repairs prior to the Super Bowl held last month in Houston. In January, the Red Line posted its highest on-time percentage, 92.6 percent, since November 2015. For many of the months between, fewer than 80 percent of the trains arrived on time.

Officials said despite the lingering issues and unresolved matters, the system is carrying people and growing. Buoyed by heavy use for the Super Bowl week, light rail weekday ridership was 2 percent higher in February, compared to the same month last year.

On Saturdays and Sundays, use was increased 12 percent and 13 percent, respectively.

“This isn’t limiting our ability to provide service,” board member Christof Spieler said of the railcar repairs.

It’s annoying that Metro is still dealing with this crap, but it will eventually get sorted. I’m focusing on the fact that the Main Street line’s on time performance has returned to normal levels, and that ridership continues to be strong. I’ve done more riding on Metro – mostly bus, but some train – in the last year than in any previous year I’ve been in Houston. The bus system redesign has been great for me, enabling my wife and I to carpool to work without having to worry about it when one or the other of us needs to go in early or stay late or run an errand after work. Sure it helps that we live in the inner Loop, but that’s where transit is most needed, and it keeps one of our cars off of I-45 every day. This isn’t directly applicable to the story here, but I think it’s good to remember that while Metro has its problems, it does do a good job at what it’s supposed to do.