The Shepherd and Durham Major Investment Project

Get ready for some major construction, but the end result will be well worth it.

Beginning next month, those who travel along North Shepherd Drive and Durham Drive in the Heights are going to have to cope with road construction – for at least the next five years.

For decades after that, though, driving down the parallel, one-way thoroughfares figures to be smooth sailing. And the same goes for walking and cycling.

Construction is expected to start in late January on the Shepherd and Durham Major Investment Project, which will overhaul the two north-and-south streets between North Loop 610 and Interstate 10 to the south while adding bicycle lanes, new and wider sidewalks, landscaping and new underground infrastructure for water, wastewater and stormwater drainage. The project could take at least five years to complete, according to president Sherry Weesner of the Memorial Heights Redevelopment Authority, which is spearheading the $115 million initiative and providing a significant portion of the funding for it.

“It’s going to take a lot of patience from all of us, but it’s going to be worth it,” said Houston City Council member Abbie Kamin, who serves the Heights as part of District C.

[…]

Protected bike lanes have been part of the plan for the TIRZ 5 project between 610 and I-10, where they will be on the east side of both Shepherd and Durham, according to Weesner. METRO bus stops on Shepherd also will be on the east side of the street because there is room to accommodate both, she said, while the bus stops on Durham will be on the west side.

New, wider sidewalks will be installed on both sides of Shepherd and Durham, where vehicular traffic lanes will be reduced from four to three on both streets with the addition of designated turning lanes at select intersections with typically heavy traffic, such as West 11th Street. Weesner said two different traffic studies showed that congestion on Shepherd and Durham was caused mostly by the absence of turn lanes at busy intersections, so there does not figure to be a negative impact on traffic flow even with the overall reduction in lanes, she said.

In addition to the work on Shepherd and Durham, the project also calls for improvements on several of the cross streets that connect them – 11th, 12th, 14th, 15th, 16th, 18th, 19th, 20th and 24th streets.

Weesner said two other features of the project are city-owned street lights and an underground bio-retention system – called the Silva Cell Tree and Stormwater Management System – that will be beneath the trees planted on each side of Shepherd and Durham. The idea is to capture stormwater to help drainage and promote the growth of large trees.

“This is a really great project, because it can do so much,” Weesner said. “The area is really changing. The area has lots of new restaurants and other facilities, and people want to be able to walk there. People need to be able to walk from one business to the next business. Improving all modes of transportation is very important.”

I like this a lot. There’s been a ton of mostly residential construction in the area, and there are now a lot of places to eat along both Durham and Shepherd. Making it easier to get around by non-car means will be a big difference maker, and will be a boost for bus riders as well. I hope they figure out a way to connect the bike lanes directly to the Heights bike trail as it passes underneath. It will be a pain going through five years of construction, but I can’t wait to see what the result looks like.

Related Posts:

This entry was posted in Planes, Trains, and Automobiles and tagged , , , , , , , , , , , , , , . Bookmark the permalink.

One Response to The Shepherd and Durham Major Investment Project

  1. Jason Hochman says:

    I’ve been waiting for this project to get started. Hopefully it will be as good as it sounds. Just walking across Shepherd and Durham is risky these past several years.

Comments are closed.