Metro board approves updated bus reimagining plan

With some provisos.

Despite vocal opposition, Metropolitan Transit Authority board members tentatively approved sweeping changes to the bus route system that restructure routes and change daily habits for nearly everyone who uses a bus today. The approval authorizes staff to move forward with scheduling and other features, but it doesn’t close off public comment.

“We can continue to work with the community and continue to work with elected officials,” said board member Christof Spieler, one of the champions of the so-called reimagining plan.

Community leaders and elected officials asked Metro to delay their decision for a month.

“Once you vote on it, they are in concrete,” said state Rep. Harold Dutton, a Democrat who represents large portions of northeast Houston affected by the service changes.

Board members settled on letting staff move forward, but in a way that permits concerned riders to voice their opposition over the next two months.

[…]

To pull off the major changes, staff will have to plan schedules for 270 routes. Some have different hours for weekdays and weekends, while others have peak schedules when ridership is highest. It is expected to take months to finalize the work, then hold more public meetings to gauge reaction before switching to the new routes in June.

Metro will continue to solicit input from the public on the plan, and will continue to make adjustments as they go. A lot of the opposition came from residents of the Fifth Ward, and a lot of their concern had to do with the proposed flex routes, which are a new and unproven idea in Houston though they’ve been used elsewhere. The Fifth Ward has a population that is both transit-dependent and shrinking, which is a tough problem to grapple with. As Christof Spieler points out in the story, there are places in Houston like Gulfton that are of a similar socioeconomic profile and equally transit dependent but which have much denser populations. These areas, which have been underserved by Metro in the past, stand to be big winners from the new bus service. How do you balance the needs while staying within the budget? There are no easy answers. Metro’s press release is here, Texas Leftist has more.

The Metro board took action on a couple of other items as well. The Highwayman reports:

Metro moved forward with other issues, but many uncertainties remain. Board members approved resolving a spat between Metro and the Texas Department of Transportation over a planned elevated bus lane along Loop 610 in the Uptown area.

The elevated lane is part of a project, led by the Uptown Houston Management District, involving dedicated bus lanes and rapid service along Post Oak Boulevard. TxDOT, which previously committed $25 million to the elevated lane, asked Metro for assurances that the project was not a precursor to rail development.

Metro officials balked at the TxDOT agreement, fearing it violated the 2003 referendum voters approved for rail projects in the Houston area. Thursday, Metro chairman Gilbert Garcia proposed approving the agreement, with the caveat that Attorney General Greg Abbott verify it doesn’t violate the referendum.

“I don’t want Metro for any way to be the reason this project is not going forward,” Garcia said.

The board also agreed that any future rail development along Post Oak would require voter approval.

Meanwhile, after acknowledging delays in opening the new Green and Purple light rail lines, Metro officials said they expect both new lines will open April 4. The delay was caused by downtown hotel construction that severed a chilled water line that required repairs to the rail system, and problems with axle counters along the lines caused by a manufacturer’s defect.

See here for the background on the former, and here for the latter. I hate giving in to the TTC’s strongarming, but the project does need to go forward, and Metro was in a precarious position. At least they have an option if the AG opinion goes their way. As for the new opening date for the Harrisburg and Southeast lines, all I can say is that I sure hope this is the last time it needs to be pushed back. Metro’s press release on that is here.

Related Posts:

This entry was posted in Planes, Trains, and Automobiles and tagged , , , , , , , , , , , . Bookmark the permalink.