Harris County on Tuesday revealed a $1.4 billion shortfall in funding for flood control projects under the bond program voters approved in 2018, a massive miscalculation that threatens to cause construction delays and cost taxpayers more than expected.
Budget Officer David Berry told Commissioners Court that projected funding from state and federal partners, which was supposed to supplement the $2.5 billion investment by county taxpayers, has not materialized. As a result, the county has committed to doing more work than it currently can afford to do.
“The hope after Hurricane Harvey that federal and state partners would really be focused on Harris County, where we saw the worst damage, has not altogether turned out to be true,” Berry said.
Berry said the county believes it can secure an additional $100 to $500 million from the state and federal governments, but that still leaves “a substantial gap.”
Projects in several watersheds are close to fully funded, though planned improvements in three — Halls Bayou, Greens Bayou and the San Jacinto River — have less than half the necessary dollars. Harris County Flood Control District Executive Director Russ Poppe said no projects will be delayed so long as the funding gap is closed by the end of this year.
The bond program currently is projected to be completed around 2028. The flood control district has spent money to design some projects in anticipation of receiving matching funds to begin construction.
[…]
Poppe said the shortfall dates back to early 2018, when Congress passed the Bipartisan Budget Act. The measure provided a collective $66 billion to the Army Corps of Engineers, Department of Housing and Urban Development and FEMA to help the country recover from the previous year’s destructive storm season, which included hurricanes Harvey, Irma and Maria.
Harris County and the city of Houston in 2019 received $1 billion each from HUD to repair and rebuild Harvey-damaged homes; the county received an additional $225 million from FEMA for buyouts.
Poppe said the county planned on receiving an additional $1 billion from HUD for flood control projects.
“The logic was … the federal government can get a level of protection on that investment they just made,” Poppe said.
That funding flowed from Washington through the state General Land Office, however, which decided instead to ask Texas cities and counties to apply for individual grants. Poppe said his office has made $900 million in requests, which he hoped would be decided later in the spring.
What’s not clear to me from this is how much of it was an over-estimation on the part of Harris County in putting together the 2018 referendum how much money from the feds and the state would be available, how much is money that we should have reasonably expected that wasn’t appropriated by the feds, and how much is just sitting there in the Land Commissioner’s office waiting to be handed out to cities and counties. All three can be addressed in one way or another, but getting the Land Commissioner to get off his ass and give us the money we’ve applied for would be the most direct. I fully expect there to be a massive infrastructure bill taken up (and hopefully passed) by Congress later this year, which can certainly include more funds for flooding projects (and maybe even the ever-elusive Ike Dike), but that depends on things that are out of our control right now. Commissioners Court has directed th flood control district to come up with a plan to secure more funds by June 30, and the commitment is there to complete the project list one way or another, which is what the voters were promised. Whatever the underlying issue is, let’s figure this out and get this moving forward.